sPHENIX PMG #60
Thursday, 20 May 2021 -
09:00
Monday, 17 May 2021
Tuesday, 18 May 2021
Wednesday, 19 May 2021
Thursday, 20 May 2021
09:00
sPHENIX status and plans for workforce on site
-
Glenn Young
(
Jefferson Lab
)
Edward O'Brien
(
BNL
)
sPHENIX status and plans for workforce on site
Glenn Young
(
Jefferson Lab
)
Edward O'Brien
(
BNL
)
09:00 - 09:10
Monthly information should include: 1) Table that shows the float of MIE components to the due date for installation 2) Near critical path activities (activities that have less than ~20 days float to the critical path for MIE and I&F). The *near-critical path* report can be set up in P6 and run automatically every month. 3) CPI & SPI reports for the I&F upgrade too. 4) Production rate for EMCAl sectors (#produced/time) compared to expectations 5) Procurements that will need attention or any issue to be raised at the POB 6) Status of PEMP notables 7) High priority issues 8) CoVID impact
09:10
Installation activities and workforce
-
Russell Feder
(
sPHENIX
)
Installation activities and workforce
Russell Feder
(
sPHENIX
)
09:10 - 09:20
1) High level summary of activities taking into account FY21, FY22 RHIC runs
09:20
Integration Test
-
John Haggerty
(
Brookhaven National Laboratory
)
Integration Test
John Haggerty
(
Brookhaven National Laboratory
)
09:20 - 09:30