sPHENIX PMG Meeting
Thursday 28 October 2021 -
08:30
Monday 25 October 2021
Tuesday 26 October 2021
Wednesday 27 October 2021
Thursday 28 October 2021
08:30
sPHENIX status, estimated at completion
-
Edward O'Brien
(
BNL
)
Glenn Young
(
Jefferson Lab
)
sPHENIX status, estimated at completion
Edward O'Brien
(
BNL
)
Glenn Young
(
Jefferson Lab
)
08:30 - 08:40
Monthly information should include: * Estimated at completion * Workforce status and needs * Table with float of MIE components to the due date for installation * Near critical path activities (activities that have less than ~20 days float to the critical path for MIE and I&F). The near-critical path report can be set up in P6 and run automatically every month. * CPI & SPI reports for MIE and I&F upgrade. * Production rate for EMCAl sectors (#produced/time) compared to expectations * Procurements that will need attention or any issue to be raised at the POB * Status of PEMP notables * High priority issues * CoVID impact