ePIC pfRICH Engineering/Design Meeting
Monday 22 April 2024 -
13:00
Monday 22 April 2024
13:00
SBU Updates
SBU Updates
13:00 - 13:15
Updates from Bill/Kong/Charles regarding summary of what has been done recently on the mirror coating/analysis and vessel production
13:15
Purdue Updates
Purdue Updates
13:15 - 13:30
Update from Andy/Sushrut regarding end ring production/simulation and mirror substrate updates.
13:30
Engineering Design Moving Forward
-
Alex Eslinger
(
employee@jlab.org;member@jlab.org
)
Engineering Design Moving Forward
Alex Eslinger
(
employee@jlab.org;member@jlab.org
)
13:30 - 13:45
Quick presentation on outstanding design items and prioritization
13:45
Mirror Mounting Scheme / Updates
-
Alex Eslinger
(
employee@jlab.org;member@jlab.org
)
Mirror Mounting Scheme / Updates
Alex Eslinger
(
employee@jlab.org;member@jlab.org
)
13:45 - 14:00
Discussion about mirror mounting scheme design as it relates to the pfRICH prototype and the final design.