Short-term goals (few weeks)
-
New B0 beampipe design exists and needs to be imported into DD4hep.
-
Alex can put in the new beampipe into DD4hep by next week.
-
Also needs to include the exit window from the IP.
-
For the EMCAL we need to somehow integrate the cooling and mechanical support into DD4hep, at least in a simplified form.
-
Yulia will share the current CAD model with Igor and Zvi to start looking into this.
-
Short-term new beam pipe + modified CURRENT detector geometry in DD4hep.
-
Do some studies with the “ideal” geometry + new pipe before updating the geometry to match CAD for the sensor layout.
-
Tracker must be 5mm from the edge of the beam pipe.
Longer-term (few months)
-
Using the B0 field map vs. using the “ideal” dipole + quadrupole.
-
How do our requirements change now that the B0 has worse acceptance than assumed in the Yellow Report?
-
1.3 GeV/c is the spec for 275 GeV – need the same for the 10x100 GeV.
Detector Technology
-
Tracking:
-
Need to freeze the stave dimensions, need to account for the new beam pipe design.
-
A stave concept has been drawn up, and initial discussion with an electrical engineer (Steve Boose, BNL) have begun.
-
Where do we place the readout?
-
2 meters is the maximum length of the cable from the ASIC to the readout card
-
Current “easiest” option is to have readout on the disks, pull fibers out of the magnet.
-
India is putting the layout together with the RP stave design - will discuss on Monday what things look like.
-
Cooling for the B0 AC-LGADs vs. the RP?
-
Can we use liquid cooling for the B0? → likely no, and may be overkill
-
Igor et al. did some studies on heat dissipation at room temperature in air for the lumi pair-spectrometer.→ Igor will send the slides around
-
EMCAL:
-
Beginning mock-up of small crystal array to start testing how to mount electronics onto crystals with our installation constraints.
-
4 + 1 crystals available to work with for now.
-
And also beginning testing with two different types of SiPMs to see what will match our constraints and requirements.
-
4x 6x6 (3 with 15um pitch, one with 10um pitch) – how to arrange the channels, still in-progress.
-
Cooling for the EMCAL is still an open-issue, important for the crystals, on top of cooling the electronics.
-
Integration of calibration fibers/system
-
.General engineering:
-
B0 mockup is ready.
-
Installation sequence:
o Bottom half of EMCAL crystals, then beampipe, then Upper half of EMCAL crystals ( See slides from Charlie). EMCAL electronics and readout will be installed later, after beam commissioning.
o Tracking layers as clam shells, in “open” position while guided to correct z-position then closed into place.