BIC System Testing Meeting
Tuesday 10 March 2026 -
09:00
Monday 9 March 2026
Tuesday 10 March 2026
09:00
DAQ Discussion for Hall D Beam Tests
-
Zisis Papandreou
(
University of Regina
)
Henry Klest
(
Argonne National Laboratory
)
Martin Purschke
(
BNL
)
DAQ Discussion for Hall D Beam Tests
Zisis Papandreou
(
University of Regina
)
Henry Klest
(
Argonne National Laboratory
)
Martin Purschke
(
BNL
)
09:00 - 09:45
A discussion among Norbert, Martin and the rest of the team to confirm our plans for the Hall D tests. Setup starts on March 24, beam comes March 30. Update: two week delay, so beam comes around mid April.
09:45
Baby BCAL new boards
-
Halen Davies
(
Graduate Student
)
Baby BCAL new boards
Halen Davies
(
Graduate Student
)
09:45 - 10:00
Progress on testing Aram's amp/summing boards.