Far-Forward Engineering Meeting

US/Eastern
Description

 

https://bnl.zoomgov.com/j/1658386942?pwd=jfdBW1OFxwIy2RZtW5c7jcQLg87afY.1

 

----------

Meeting topics:

*Roman pots design discussion
    --Impedance calculations (updates, if any)
    --vacuum constraints
*Geometry updates
*AOB

 

 

Short update on impedance

  • Gang showed results at a previous IR meeting - no major red flags with RP configuration he got from Karim.
  • Karim will supply Gang with the 275 GeV location for the planes for another simulation.

 

Geometry updates in DD4HEP

  • Alex is still working on adding the current CAD model into DD4HEP and checking the acceptances, et al.
  • Goal is to evaluate the acceptances with each subsequent change:
    • First update RP layout.
    • Next, add additional material into the layers (Copper cooling/RF shielding).
    • Then, add outer rim of copper (affects low-pT acceptance, but how much?).
    • Update beam pipe and scattering chamber dimensions.
    • Add basic flanges and bellows.

 

Additional aspects of the vacuum system which require further follow-up

  • Various transitions between pipe section, bellows, flanges, etc. will all have impact on detectors (how much depends on the item in question) --> this needs to be evaluated in the simulations, as well (Alex).