KEK Test Beam Schedule and Shift Planning

  • The test beam in collaboration with the ALICE3 team is booked from December 11, 2026, to December 19, 2026.
  • The dedicated time slot for AC-LGAD and FCFD runs for two days, from December 17, to December 19, operating on a 24-hour shift schedule.
  • Parasitic setup and commissioning can take place between December 11, 2026, and December 16, 2026, while the telescope is commissioned by the MOSAIX and SPARK teams.
  • Due to the EIC workshop in Japan during the AC-LGAD test period, Japanese student availability is limited, making US participant coverage (especially for overnight shifts) valuable.
  • Conclusion: A shared spreadsheet will be created to organize shift sign-ups, responsibilities, and participant logistics.

FCFD v1.2 Development and Test Beam Readiness Status

  • Standalone chip evaluation is currently underway, including bench testing of analog/digital components and firmware development.
  • The team only has half-size sensors and one full-size sensor on hand; additional sensors are needed (ideally 4–5) to ensure reliable testing.
  • Readout boards for the full-size sensor are scheduled to be submitted for manufacturing within the current week.
  • Readiness will be reviewed before committing to travel, as firmware, sensor mounting, and DAQ integration must function properly to justify travel.

Equipment, Logistics, and Backup Test Beam Plans

  • The setup will use EUDAQ for data acquisition; the team will bring their own KCU105 FPGA board and requested backup KCU105 boards from the host if available.
  • Minimal on-site equipment is required (power supplies, high/low voltage units, computers).
  • Hand-carrying additional sensors during US visits was discussed to circumvent shipment paperwork delays.
  • A proposed test beam at KEK in February 2027 serves as a secondary backup.
  • A potential third backup option was noted at DESY in late May 2027 during the pixel sensor test beam led by Alex.
  • Conclusion: The next progress and readiness evaluation meeting is scheduled for November 18, 2026, at 9:00 AM Chicago time.

 

Next Arrangements:

  • Create and share a spreadsheet to manage shift sign-ups and task assignments for the KEK test beam.
  • Send KEK registration, entry requirements, and training information to US participants.
  • Provide the host facility with a list of required equipment and power supplies.
  • Submit the new readout board design to house full-size sensors within the current week.
  • Coordinate with Simone and Taku to clarify sensor availability and ship/deliver 4–5 additional sensors (consider hand-carrying to avoid paperwork delays).
  • Define a cutoff date for the go/no-go decision on FCFD firmware, sensor mounting, and DAQ integration readiness prior to travel.
  • Plan the EUDAQ and MAPS synchronization timeline to ensure integration is completed before the December 17 run, accounting for personnel arrival dates.
  • Convene a follow-up readiness evaluation meeting on November 18, 2026, at 9:00 AM Chicago time.