*Updates from Tonko on EICROC1 testing w/ LPGBT
*Updates on lab testing from BNL
*AOB

Update from Tonko

  • Same updates shared in DAQ meeting.
  • Discussion of the RP stave/module board.
    • Slightly modified plan --> aiming for standard FR-4 boards with 2 week turnaround time, and 10cm shortening of overall "cable" in response to the update design with RDOs in-vacuum.

 

Discussion of BNL lab setup & DESY testbeam

  • BNL lab setup essentially ready now to build required testbeam apparatus and test the full chain readout with e.g. external trigger detector. 

 

RCDAQ for testbeams