Integration of TOF-PID Detectors into EPIC

US/Eastern
Zoom

Zoom

Constantin Loizides (ORNL), Frank Geurts (Rice University), Wei Li (Rice University), Zhenyu Ye (University of Illinois at Chicago)
Description

Zoom meeting: https://uic.zoom.us/j/87271164194?pwd=RExlQm1SSGpXZkovVWtid0RVdVo1QT09

Meeting ID: 872 7116 4194
Passcode: EICTOF22

Dial by your location
        +1 312 626 6799 US (Chicago)
        +1 646 876 9923 US (New York)
        +1 646 931 3860 US
        +1 301 715 8592 US (Washington DC)
        +1 346 248 7799 US (Houston)
        +1 408 638 0968 US (San Jose)
        +1 669 444 9171 US
        +1 669 900 6833 US (San Jose)
        +1 253 215 8782 US (Tacoma)
Meeting ID: 872 7116 4194
Passcode: 94657300

    • 11:00 11:20
      TOF Design 20m
      Speakers: Constantin Loizides (ORNL), Frank Geurts (Rice University), Prof. Wei Li (Rice University), Zhenyu Ye (University of Illinois at Chicago)
    • 11:20 12:00
      Roundtable Discussion 40m
      Speaker: All

      Minutes: 
      1. CTTL: If we need to move CTTL in/out for maintenance, we need to mount it on a rail system. Otherwise we can mount the CTTL staves on the DIRC surface and support at 3-4 points along the staves (Integration)
      2. ETTL: large power consumption can be a concern: 1) introduce a strong heat source near EEMC crystals, the material of a thermal screen to isolate ETTL and EEMC might degrade EEMC performance; 2) material of ETTL itself if too much can degrade EEMC performance.  
      3. FTTL: need to make the FTTL outer diameter smaller to make space for inner detector cable/service routing (Integration).
      4. We can ask project for engineering design support.
      5. Tim sent questions by email and Wei/Zhenyu answered in their presentations. 
      6. We will have a follow-up meeting in 4-6 weeks from now.

      Elke:
      There can be space for a backward tof, but the 10 cm needed for the tof will impact the space available for the tracking. The main challenge is the cooling and needs to be figured out as it has impact on the electron endcap ECal, due to the temperature dependence of the PbWO4 crystals. It was also pointed out that a heat sink in front of the electron endcap ECal is not an option, becuase of performance issues. I would also like to say that the heat, which needs to be taken out is also a concern for the hardron endcap and needs to be addressed also for the barrel, but to a lesser extend becuase of the larger pixel size.

      Rolf:
      per my best knowledge there are definite issues, especially in the backward direction where we have to mitigate materials and can not afford cooling solutions. So we in the Project would definitely not support stating "including the backward TOF".