From Beni:
Rolf asked me to find a time to meet and talk about the cost/schedule of
TOF.
The reason is that what is currently in the project is significantly
lower and
the projects needs to understand where the increased cost in materials is
as it is in total about 5M for the barrel from the original proposal.
While in
the current TOF estimate it is about 10M a factor of two higher.
The problem is that in such a scenario the detector might become
unaffordable,
without substantial in-kind contributions.