the project would like to encourage you collect your ideas about building the staves for the TOF
and creating a flow chart that visualizes the your ideas as to what the individual steps are to build the staves
and where.
The reason we ask for such an flow chart is to understand what steps are involved and in particular what
may need to be shipped between different production sites and where these production sites are.
Once you have such a flow chart we can organize a meeting with the project to discuss the implications
it may have with regards to shipping, overhead, spare parts, expected failure rates and the like.