[Itaru: Update on the NIM paper]

- Allowance is determined by the FPHX output (tunable) and the receiver threshold (fixed) on ROC and it is independent of the length of the cable.
- Percentage on the water absorption is the material budget.
- If the cable absorb water, transmission rate will be degraded. The number is written in the catalog.

- 70% loss for the 2mA, which is very closed to the allowance. Set the output 6mA of 2mA.
- Will resubmit the updated draft on next Tuesday or Wednesday. Please send your feedback by then.


[Yuko: Offline QA plot]
- For the offline QA plot guidance, remove old ones (phi size distribution, z vs phi map), then just put Jaein's new plots in the guidance


[Tomoki: Update on the half entry issue]
- You should check multiple runs to check chip#21 to see the how much unstable it is.
-- Already checked the recent runs and it is actually unstable.
- Things to do before implementing the new digital control parameters permanently for physics runs?
-- Check adc distribution of the healthy chips with/without the special digital control.
-- Will report at a SCM next week and will take some data with the updated digital control parameter.
-- Need to compare the file size of intt7 with other intt servers file, to make sure if it is not super hot to cause any DAQ issue.