Minutes BHCal Meeting, 2/27/26
—————————————————
Spare Tiles—Murad
- Murad got quote from Eljen
- $0.5M for raw, not even cut tiles
- were hoping to get ready tiles (cut, grooved, with fiber glued, (ideally also coated), wrapped for $0.4M
- so this is not viable
- ideas to pursue other options were discussed
Read-Out—Martin (see slides)
- 10 Gb/s decoding solved with firmware change that slowed down PLL
- RCDAC capability to record data with multiple settings in same run
- used by Norbert for parameter scans
Calibration—Jan
- progress on MC for 1 GeV neutrons
- also studying protons now
- also going to lower energies
- update next week