    • 19:00 19:20
      Beam Test at Jlab and DESY and Japan updates? 20m

      Feb 19-25 at KEK, first week of March

      JLab testbeam results:
      https://drive.google.com/file/d/1O-Y1ByGy6GPxHMMKGyODMDPGZAW5nWI4/view
      test beam facilities:
      https://test-beam-facilities.web.cern.ch

      paper out on irradiated AC-LGADs from last year: https://arxiv.org/abs/2503.16658
      We did another round of irradiation with neutrons on some AC-LGADs but at extreme fluence, plus another irradiation campaign with protons on the large AC-LGADs that should be ready soonish.
      SEB studies from BNL: https://indico.global/event/14966/contributions/133281/attachments/63257/122069/SEB_CPAD_2025.pdf

      Cheers,
      Simone

    • 19:20 19:40
      scheduled discussions on action item tracker 20m

      Dear TOF consortium ,

      We should meet to discuss about the progress on TOF action tracker

      https://www.dropbox.com/scl/fi/y3jj66yax7c05rtf2g258/TOF_Schedule_activities_v1.xlsx?rlkey=7532tcaf8f1z69h4wp37nbtfq&st=j133n88y&dl=0

      I am planning to call for meeting on Wednesday of February 11, 2026 @ 10:30 AM (EST) which was usually the time for TOF general meeting. Unfortunately, there has not been any entry in the progress section of the action tracker. We need to touch base on progress on the following action items

      We have discussed BTOF last week, and this week if FTOF experts are available

      FTOF :

      ASIC and sensor heaters construction
      Assemble second module based on module V1 with heaters
      Thermal testing on module v2

      @Benoit, Mathieu all the listed activities has start date of on or after 10/30/2025. I suppose activities before that dates are finished so please update the action tracker with the appropriate "Status"

      Pixel Sensors :

      Population of "etched" assembly for IJCLab testing
      Testing (TCT and Sr-90) of etched assembly

      I will send out the zoom invite soon.

      Best regards,
      Surabhi

    • 19:40 20:00
      FTOF hit occupancy? 20m