Commissioning plan

21 Jul 2020, 16:25

Description

Commissioning plan (partially covered in 2), but as you listed software separately - we'll need to hear current status of software we'll need for commissioning.
The goals are:
a) identify missing components
b) identify person(s) who will be able to continue to do most of lifting during next couple of years as well.
Commissioning will continue through Run21/22 and being involved in this from the beginning is very important.

Presentation materials

There are no materials yet.
Previous tabNext tab
Print
PDF
Full screen
Detailed view
Filter
16:00
17:00
Akio Ogawa et al.
Commissioning Software update of what we already have and what is missing
16:25 - 16:55
Paul Nord
Slowcontrol Status
16:55 - 17:25