INTT Weekly meeting
This is a memo from the last INTT meeting.
-- Schedule
No summer break expected.
The Travel schedule is updated.
The schedule table should be updated accordingly
-- Analysis tasks using new beam data in 2025
Tasks are listed in the table
https://docs.google.com/spreadsheets/d/175Z06nDFWACKIrvqN_R43ABLtRfE6r23u9CZtVuwDHg/edit?gid=1538604329#gid=1538604329
People cover many topics. But some topics are still open. Need volunteers, especially people from outside of BNL.
-- Software comments: Joseph
- The way to implement is explained
- Implementation and checking will be started from now.
- Takashi requested to make some slides to explain how the consistency of the output is checked.
-- Beam test analysis: ChengWei
- The systematic uncertainty of the DAC scan is updated
- Takashi and Genki asked about the choice of the normalization method, asymmetric systematic uncertainty,
how to fit the DAC histogram, and how to calculate the systematic uncertainty of the S/N from the DAC histogram.
- Discussion continues offline
- The efficiency evaluation is updated.
- The residual window is wider to cover the almost 100% efficiency region
- Y dependence of the efficiency shows the asymmetric uncertainty
- Total efficiency is calculated using Ncounts, including all Y ranges.
- not combine the Y dependent efficiencies to obtain the total eff.